Shivalik Platinum

Ahmedabad, India
SP PRXL

Challenges Faced

  • A large open sewer was discovered right beside the Diaphragm wall during construction.
  • The project was in close proximity to other ongoing constructions and completed structures.
  • Managing the logistics was tricky as the main street had huge traffic flow.
SP SQUARE 1

Solutions Provided

  • CLSM Concrete was used as fill between the wall and the pipe, making the grabbing and panel casting possible.
  • The project site was well enclosed to ensure none of the nearby residents faced any difficulty.
  • All the required materials were sourced well in advance to prevent unnecessary movement.

Media

A sneak-peak into how the project was executed by our professional and efficient teams.